|
Former Henry Woods Sons Paint Factory, Wellesley,
Massachusetts
Project Profile:
The remediation of this abandoned pigment manufacturing facility resulted in
the transformation of this property into an active recreational sports complex
and nature trails. East Coast Engineering accomplished this difficult
conversion through a comprehensive understanding of waste site cleanup
initiatives, engineering design, and facilitating communication between the
property owner, the community, and local, state and federal regulatory
stakeholders. Historical operations at the 19th century pigment manufacturer
resulted in metal contamination of nearly 200 acres of uplands, wetlands, and
surface water bodies. Extensive applied forensic investigation of historical
documents, mapping, and research of the Henry Woods site and of other
turn-of-the-century pigment and paint manufacturers resulted in a comprehensive
knowledge of type of materials produced, waste generation, facility layouts,
and common industrial practices.
East Coast conducted a comprehensive site assessment to characterize the metals
contamination at the site, evaluated risks of harm to public health, safety,
public welfare and the environment and developed remedial design plans for the
off-site management of pigment and consolidation and encapsulation of metal
contaminated soil and sediment. East Coast planned and provided construction
oversight for a 1.6 million dollar removal action of 4,000 cubic yards of waste
pigment and closure of former waste pile areas and a former lagoon. Following
these initial response actions, and further site characterization, East Coast
developed innovative conceptual plans incorporating the remediation design for
the entire site of encapsulation of contaminated media with post-closure use
and redevelopment of the property as an active recreational sports complex.
This remedial design resulted in the beneficial use of greater than 50 acres of
prime real estate and at a substantial savings to the client.
Construction & Demolition
Landfill, Massachusetts
Project Profile:
A polyurethane polymer concrete material disposed at a construction and
demolition debris landfill resulted in the leaching of tetrachloroethylene
(PCE) into the groundwater. Nearby residential water supply wells and cranberry
bogs immediately adjacent to and downgradient of the landfill were potentially
at risk. Environmental forensic techniques were used to locate 800 tons of
polymer concrete and predict its’ behavior in the landfill environment.
Extensive hydrogeological assessment of a complex aquifer beneath the landfill
and throughout nearly 300 acres of study area found that landfill conditions
caused rapid biodegradation of PCE to vinyl chloride. However, the resulting
vinyl chloride contaminant plume was greater than 80 feet below the ground
surface and migrating with the groundwater at a rate of one foot per day. East
Coast was instrumental in determining the extent and fate of the volatile
organic plume and designing and implementing multiple risk reduction measures
including a residential vapor and water supply monitoring program and
contingency plans for providing municipal water into a town with no municipal
water sources. Permanent remedial measures designed for the site included
capping and closure of the source area and landfill with a multi-media system
to prevent future releases of PCE without disruption of landfill activities,
extending a municipal water supply to residential homes and implementation of
an in-situ enhanced bioremediation system to treat the contaminated
groundwater.
East Coast worked closely with multiple departments of the Massachusetts
Department of Environmental Protection and local agencies on this complex
regulatory project; developed and implemented a community awareness and
education programs at the onset of the project to establish positive
communication between the clients and the community; and coordinated with four
potentially responsible parties with diverse concerns to ensure forward
progression of the project towards remediation.
Belle Isle Fish Company, Boston, Massachusetts
Condor Street, Boston, Massachusetts
Project Profile:
The Belle Isle and Condor Street waste sites were selected by the City of
Boston for remediation and re-development into parks and re-created salt
marshes. Both properties were formerly used for industrial/commercial purposes
and over the years had undergone historic filling with construction debris and
soils contaminated with petroleum-related compounds, metals and polychlorinated
biphyenyls (PCBs). A comprehensive soil characterization program was undertaken
to delineate and quantify the nature and extent of contamination with the focus
on determining whether re-development of these properties was feasible. The
results of the feasibility analysis found that the most optimal solution
included the on-site re-use of soils landscaped to create a park-like
environment with the most highly contaminated soil managed off-site.
East Coast prepared remedial design plans and construction specifications for
contractor operations and provided oversight during construction activities
which included the removal of solid waste debris including cars, barges and
demolition materials from the shoreline; excavation, consolidation and
encapsulation of contaminated soils into park-like features; stabilization of
shoreline using steel sheeting piles; and re-establishing a salt-marsh
environment. Both projects involved obtaining multiple local, state and federal
permits to conduct the remediation work in an inter-coastal waterways and
participation in community outreach programs. East Coast aided the legal
pursuit of the parties responsible for the contamination resulting in the
recovery of substantial costs for the City.
Berkshire Hathaway Mill Complex, New Bedford, Massachusetts
Project Profile:
At a former textile mill complex, East Coast provided LSP Services, forensic
investigation, groundwater characterization and remediation oversight relative
to historical No. 6 petroleum releases.
A forensic analysis was conducted to determine the source of release of No. 6
fuel oil into a water pump chamber; assessment and remediation of a 100,000
gallon underground fuel storage tank and associated fuel distribution system
including the underground piping, pump chambers, trenches and sumps; and
preparation of remedial design and construction plans.
Remedial plans were developed for the cleaning and permanent removal of the
underground concrete storage tanks and associated fuel distribution pumping
chambers and lines along with contaminated soil. Unique challenges encountered
during this remediation project included the location of the underground tank
within five-feet of the 5-story brick mill building, numerous underground
utilities located adjacent to the former tank and the overhead catwalks and
construction columns impeding soil removal. Construction oversight and record
keeping were provided during the removal action, conducted as a Release
Abatement Measure, which included removal of over 850 tons of petroleum
contaminated soil and approximately 10,800 gallons of oily water.
Post-remedial action assessment included groundwater and air quality within and
beneath adjacent buildings to assess extent and potential impact of petroleum
and inorganic contamination and impact to indoor work environments.
American Fiber & Finishing,
Colrain, Massachusetts
Project Profile:
Historic releases of No. 6 fuel oil from 3-25,000 gallon underground storage
tanks resulted in extensive soil, surface water, groundwater, and sediment
contamination at a former cotton manufacturer. In support of this complex
environmental assessment, East Coast gathered forensic data and evaluated
chemical fingerprinting data in support of dating the releases of oil from the
site in support of litigation and identifying the petroleum type. The
complexity of the site and extent of oil migration led to an expanded remedial
design which included the demolition of several buildings; shoring of a state
road adjacent to the site to maintain the flow of traffic during remedial
activities; re-routing a surface water canal away from the contaminated area
without the interruption of service to a neighboring factory; and the off-site
removal of contaminated soil and sediment. This project presented a unique
challenge of completing the demolition and cleanup with minimal impact to an
adjacent river bank and wetlands area. Groundwater and surface water
remediation during construction included extraction and carbon treatment with
an NPDES permit to the North River. East Coast provided extensive public
relations and community outreach prior to and during construction activities.
Twinkle Cleaners, Raynham, Massachusetts
Project Profile:
Provided technical support and expert testimony in a case brought against
Twinkle Cleaners by the property owners. Ms. LeBlanc’s testimony, on behalf of
Twinkle Cleaner, addressed the characterization of volatile organic compounds
(VOCs), and the fate, transport and degradation of VOCs in groundwater. The
testimony resulted in Twinkle Cleaners not being held as a responsible party
for the release of VOCs in the site’s groundwater.
Downgradient Property
Project Profile:
Ms. LeBlanc provided technical support to a private developer of a nearly
400-acre residential golf resort where a portion of the real estate was
contaminated by the release of chlorinated volatile organic compounds from an
upgradient industrial property. Through forensic evaluation of an industrial
facility and the knowledge and application of biotransformation of organic
compounds in the groundwater, Ms. LeBlanc was able to establish the sources of
multiple releases and timeframe of the releases. Ms. LeBlanc’s testimony not
only resulted in a significant monetary settlement for the downgradient
property owner, her technical credibility and capacity to provide clear concise
information to potential buyers fostered property sales.
Polymer Concrete Project, Massachusetts
Project Profile:
Ms. LeBlanc is providing technical and expert witness testimony in a case
involving the migration and fate of volatile organic contaminants in the
groundwater and treatment of the impacted groundwater. This case results from
the disposal of over 800 tons of a polyurethane concrete material at an unlined
solid waste landfill in Massachusetts and the release of tetrachloroethylene
from the concrete matrix into the groundwater. The case is complicated by
several cross suits, impacts to the groundwater on multiple private properties,
and potential impacts to residential private water supplies throughout the
study area.
Cohen Landfill, Taunton, Massachusetts
Project Profile:
Operations at a former salvage yard and metal recycling company resulted in
soil and groundwater contaminated with volatile organic compounds and
polychlorinated biphenyls (PCB’s). As a designated Brownsfield project, the
City of Taunton contracted with East Coast to prepare the design and contract
specifications to remediate the site which included the excavation and off-site
removal and chemical treatment of over 10,000 cubic yards of contaminated soil,
an on-site stormwater conveyance system, and the grading and capping of a
landfill area. An integral component of this project involved designing the
remediation scheme to incorporate the post-closure use of the property as the
City of Taunton’s public works salt storage and vehicle maintenance area.
Post-closure environmental monitoring and inspection of the integrity of the
closure system are conducted to ensure the effectiveness of remediation.
Quarry Hills Recreational Complex, Quincy,
Massachusetts
Project Profile:
The construction of a 27-hole golf course and recreational complex over the
former Quincy and Milton municipal landfills offered unique challenges
involving an environmentally and politically sensitive arena, complex
regulatory issues and engineering applications. East Coast completed
permit-level designs, specification and application to use about 11 million
cubic yards of excavated material from the Boston Central Artery project to
reconfigure the landfill. The comprehensive construction designs included
stormwater management systems to minimize off-site migration of the excavated
materials and stormwater storage systems for reuse of stormwater for irrigation
purposes. The complex civil site design of this project included the
construction of a luxury clubhouse over the landfill incorporating underground
utilities, landfill settlement techniques, and gas management systems.
Ravenbrook Landfill, Carver, Massachusetts
Project Profile:
Ravenbrook Landfill is a construction & demolition debris landfill
operating from the late 1970’s to the mid 1990’s. East Coast was contracted to
modify the original closure designs and to oversee construction of the
multi-media capping system for the 25-acre landfill. Modifications to the
original design saved the client approximately $750,000 in construction costs.
East Coast was involved extensively with the regulator agency soliciting input
and approval of changes. Maintaining ongoing communication with regulators
ensured the smooth completion of the project in compliance with the solid waste
regulations and at a savings to the client. Post-closure monitoring and
maintenance continues to demonstrate the effectiveness of the capping system.
Bedminster-Marlborough, Massachusetts
Project Profile:
Bedminster-Marlborough is the first Municipal Solid Waste (MSW) compost
facility in Massachusetts to be permitted and operational. The project
consisted of design and permitting for a 500 ton per day MSW/Biosolids compost
plant and citizen’s recycling center. East Coast’s site specific designs
tailored Bedminsters’ system to work in a low-lying valley near residential
neighborhoods to ensure that nearby residents did not fall victim to odor
problems. A roof over Bedminster’s biofilter system allowed the air to be
released higher into the atmosphere and diffuse before odor was recognized.
East Coast played an intergral role in mediating issues of odor management
between the homeowners and the City of Marlborough. These community actions
helped gain citizen support for the Bedminster facility.
Leominster Transfer Station, Leominster, Massachusetts
Project Profile:
East Coast designed and permitted the Leominster Transfer Station to include
facilities for separated residential recyclables, commercial waste recycling
facilities, construction and demolition material processing and yard waste
management, and solid waste transfer activities. A key component of the design
is the segregated Municipal Solid Waste and Construction & Demolition
tipping floors, allowing for separation of the various components of the waste
stream. Working with local officials and community members, East Coast also
designed this facility to provide for increased recycling opportunities and
easy access for residents.
|